Residuals Handling Facility

Progress pictures of theĀ Residuals Handling Facility in Dickinson.

Rice Lake finishing the concrete surface on the underside of the second floor concrete slab.

Rice Lake finishing the concrete surface on the underside of the second floor concrete slab.

Rice Lake started finishing the walls in the basement pump room.

Rice Lake started finishing the walls in the basement pump room.

Looking east at the bottom of the precast concrete roof beams.

Looking east at the bottom of the precast concrete roof beams.

Looking southeast at the building during the sandblasting operations.

Looking southeast at the building during the sandblasting operations.

Protech began sandblasting the bottom of the second floor slab and the first floor columns.

Protech began sandblasting the bottom of the second floor slab and the first floor columns.

Protech sandblasting the underside of the second floor concrete slab.

Protech sandblasting the underside of the second floor concrete slab.

Looking south at the construction site.

Looking south at the construction site.

Rice Lake finishing the surface of a second floor concrete beam.

Rice Lake finishing the surface of a second floor concrete beam.

Rice Lake removed the plywood used to protect the first floor concrete slab.

Rice Lake removed the plywood used to protect the first floor concrete slab.

Rice Lake bushing the concrete slab at filter press #1.

Rice Lake bushing the concrete slab at filter press #1.

Rice Lake removing the decking from the underside of the second floor slab.

Rice Lake removing the decking from the underside of the second floor slab.

Looking east at filter press #1 equipment pad.

Looking east at filter press #1 equipment pad.

Waterproofing and drainage board placed on west side of building.

Waterproofing and drainage board placed on west side of building.

Unlimited Excavating compacting structural backfill along the east and south sides of the building.

Unlimited Excavating compacting structural backfill along the east and south sides of the building.

Waterproofing and drainage board placed on north side of building.

Waterproofing and drainage board placed on north side of building.

Looking south at the first to second floor between grids 4 to 5.

Looking south at the first to second floor between grids 4 to 5.

Rice Lake cleaning the decking for the 2nd story slab pour #2.

Rice Lake cleaning the decking for the 2nd story slab pour #2.

Unlimited Excavating installing fill material on the western side of the structure.

Unlimited Excavating installing fill material on the western side of the structure.

Looking west at installation of the second floor trench drain and construction joint bulkhead north of filter press 2.

Looking west at installation of the second floor trench drain and construction joint bulkhead north of filter press 2.

Looking west. Rice Lake removing form imperfections in the concrete along the south wall.

Looking west. Rice Lake removing form imperfections in the concrete along the south wall.

Looking east. Setting of masonry block on the south side of the 1st floor.

Looking east. Setting of masonry block on the south side of the 1st floor.

Looking south. Erection of the framework for the 2nd floor deck in progress.

Looking south. Erection of the framework for the 2nd floor deck in progress.

Looking west. Rice Lake removing forms from the columns placed earlier.

Looking west. Rice Lake removing forms from the columns placed earlier.

Looking west. Rice Lake setting forms for the first to second floor columns at grids 4 to 6.

Looking west. Rice Lake setting forms for the first to second floor columns at grids 4 to 6.