Southwest Pipeline Crossing Permit Application


In accordance with section 61-24.3-20 of the North Dakota Century Code, crossing of the Southwest Pipeline Project (SWPP) easement requires prior approval to the extent the Project has authority to do so. Southwest Water Authority (SWA) in accordance with section 61-24.5-01 and through the transfer agreement with the North Dakota State Water Commission, manages, operates and maintains the SWPP. Approval will therefore be granted by SWA based upon signed acknowledgement of and intent to comply with the following conditions:

  1. Applicant will assume full responsibility for any and all damages caused by the construction, operation and maintenance of the applicant’s facilities.
  2. Applicant’s facilities will cross beneath the SWPP pipeline if at all possible. (Does not apply to natural gas lines, power lines and communication systems buried less than 48 inches).
  3. At the point of crossing, a minimum separation of 18 inches must be maintained between the applicant’s facilities and the SWPP pipeline. Exceptions must receive prior approval.
  4. Excavation in the vicinity of our pipeline shall be performed by hand digging only. Our main transmission pipelines must be exposed whether boring or open cut methods are utilized.
  5. Crossing angle shall be as near 90 degrees as possible.
  6. Applicant shall envelop the SWPP metallic pipelines with a granular material similar to the material removed. This requirement does not apply to PVC pipelines.
  7. Applicant must mitigate any interference with the SWPP cathodic protection system. Any installation of cathodic protection shall be subject to inspection by SWA personnel.
  8. Crossing shall be inspected by SWA personnel prior to and during backfill. No charge will be made during normal working hours. Outside of normal working hours applicant will be billed for the onsite representative(s) at billable rates plus mileage and any other related expenses.
  9. Pipelines carrying products other than potable water must be encased a distance of 20 feet on either side of the crossing. (Natural gas is exempt from this requirement).
  10. Applicant must provide a minimum of 48 hours notice prior to construction activity.
  11. Applicant will indemnify and hold harmless SWA, and its officers, directors, employees, and contractors, from and against all claims, costs, losses, and damages, including those claims arising out of or relating to the performance of SWA’s water distribution system at the crossing location(s), as long as any such claim, costs, losses, and damages were caused by the applicant’s project or the existence of applicant’s facilities.
  12. Applicant will procure and maintain insurance appropriate to cover claims that may arise resulting from the applicant’s project or facilities. The applicant’s insurance policy shall insure all operations by or on behalf of the Company, on an occurrence basis, against:
    • Claims for damages because of bodily injury, sickness or disease, or death of any person.
    • Claims for damages insured by reasonably available personal injury liability coverage.
    • Claims for damages because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom

    The limits of liability for the insurance required by the preceding paragraph shall provide coverage for not less than the following amounts or greater where required by law:

    • General Aggregate: $2,000,000
    • Products – Completed Operations Aggregate: $2,000,000
    • Personal and Advertising Injury $1,000,000
    • Each Occurrence (Bodily Injury and Property Damage) $1,000,000
    • Excess or Umbrella Liability Per Occurrence $1,000,000
    • Excess or Umbrella Liability General Aggregate $2,000,000
    • Contractor Pollution Liability Each Occurrence $1,000,000
    • Contractor Pollution Liability General Aggregate $1,000,000

    The applicant’s commercial general liability, umbrella or excess, and pollution liability policies shall include and list as additional insureds SWA and its officers, directors, employees, and contractors; and the insurance afforded to these additional insureds shall provide primary coverage for all claims covered thereby (including as applicable those arising from both ongoing and completed operations) on a non-contributory basis. The applicant shall obtain all necessary endorsements to support these requirements. Upon issuance of the Crossing Permit requested by this application, the applicant shall deliver to SWA certificates and other evidence of insurance required to be provided by applicant.

If these conditions are agreeable, please note proposed crossing location details on the back side of this form and/or attach maps or drawings. Each crossing will require a separate permit unless authorized to provide a blanket permit for large projects with multiple crossings. Blanket permits shall require location identification and/or maps or drawings of each crossing. The application must be signed by the owner or an authorized representative of the facilities. Contractor signatures are not acceptable. Upon approval, the applicant will receive copies of the Permit and this form for the applicant’s records.

Download the application by right clicking on the button below. Select 'Save Target As' and select where you would like it downloaded on your computer. You can also left click the button to open the document in a new window and save it from your pdf viewing program or application. Proceed accordingly. If you have any questions, contact us at Southwest Water Authority.